Deliverables to be provided by ETICS 2 to the European Commission as agreed in Annex 1 ("Description of Work") of the ETICS 2 Grant Agreement.
No.
Deliverable Name
WP no
Leader
Delivery
Status
DNA1.1
Project management information system and tools
NA1
CERN
M01
Delivered
DNA1.2
Quality Assurance and Progress Monitoring Plan
NA1
CERN
M01
Delivered
DNA1.3
First period progress reports
NA1
CERN
M12
Delivered
DNA1.4
Final period progress reports
NA1
CERN
M24
Delivered
DNA2.1
Training Plan
NA2
CERN
M03
Delivered
DNA2.2
Dissemination and Use of Knowledge Plan (First Update)
NA2
ENG
M06
Delivered
DNA2.3
ETICS Grid Quality Certification Model activity report (year 1)
NA2
ENG
M09
Delivered
DNA2.4
First year analysis of training and tuning activities
NA2
CERN
M12
Delivered
DNA2.5
Dissemination and Use of Knowledge Plan (Second Update)
NA2
ENG
M12
Delivered
DNA2.6
Long-term sustainability strategy and activity report (first release)
NA2
ENG
M12
Delivered
DNA2.7
ETICS Grid Quality Certification Model activity report (year 2)
NA2
ENG
M18
Delivered
DNA2.8
Dissemination and Use of Knowledge Plan (Third Update)
NA2
ENG
M18
Delivered
DNA2.9
Long-term sustainability strategy and activity report (final)
NA2
ENG
M21
Delivered
DNA2.10
Second year analysis of training and tuning activities
NA2
CERN
M23
Delivered
DNA2.11
Dissemination and Use of Knowledge Plan (Final)
NA2
ENG
M24
Delivered
DSA1.1
Execution plan for first 12 months of infrastructure operation
SA1
CERN
M03
Delivered
DSA1.2
ETICS Core Services Design Specification
SA1
CERN
M06
Delivered
DSA1.3
ETICS Site Service Level Agreement
SA1
CERN
M09
Delivered
DSA1.4
Execution plan for second 12 months of infrastructure operation
SA1
CERN
M12
Delivered
DSA1.5
ETICS core services certification and usage report
SA1
CERN
M21
Delivered
DSA2.1
User Support Procedures
SA2
INFN
M03
Delivered
DSA2.2
New infrastructures evaluation plan
SA2
INFN
M06
Delivered
DSA2.3
Infrastructure services integration - Analysis
SA2
INFN
M06
Delivered
DSA2.4
Infrastructure services integration – Implementation (Part 1)
SA2
INFN
M12
Delivered
DSA2.5
Guidelines for adopting ETICS as build and test system
SA2
INFN
M15
Delivered
DSA2.6
Infrastructure services integration – Implementation (Part 2)
SA2
INFN
M20
D
elivered
DSA2.7
Infrastructure Services Integration
-
Implementation (part 3)
Additional information
Delivered
DJRA1.1
Job Management Web Service Interface Specification
JRA1
UoW
M03
Delivered
DJRA1.2
IPv6 Compliance Analysis
JRA1
UoW
M09
Delivered
DJRA1.3
Integration of Virtualization Technologies (prototype)
JRA1
UoW
M12
Delivered
DJRA1.4
Job Management Web Service Interface Implementation
JRA1
UoW
M15
Delivered
DJRA1.5
Integration of
V
irtualization Technologies (final)
JRA1
UoW
M18
Delivered
DJRA1.6
IPv6 Compliance
JRA1
UoW
M20
Delivered
DJRA2.1
Use Cases Specification
JRA2
4DSOFT
M04
Delivered
DJRA2.2
Test interface standards
JRA2
4DSOFT
M06
Delivered
DJRA2.3
Test tool registration system (prototype)
JRA2
4DSOFT
M12
Delivered
DJRA2.4
User interface and Test Execution Generator (prototype)
JRA2
SZTAKI
M12
Delivered
DJRA2.5
Test management system (prototype)
JRA2
4DSOFT
M18
Delivered
DJRA2.6
Complete test management system (final release)
JRA2
4DSOFT
M22
Delivered